TRES LAGOS

TIMELINE
Here’s our projected timeline:
Tree Cutting & Removal
In progress and scheduled to complete on or around September 16th, 2023.
Grading
Approximately August 15, 2023 – September 15, 2023.
Site Utilities & Building Foundations
September 15, 2023 –
February 28, 2024.

Framing & Building Utilities
January 15, 2024 – April 15, 2024.
Project Completion
Approximately February 2025.
Leasing
March 2025.